PJM Asks FERC to Halve Grid Connection Studies for Data Centres to One Year
The largest US grid operator also wants data centres of 50MW or more to ride through disturbances, after nearly 3.9GW switched to onsite generators on July 22.
·3 min read
Prefer Nakoda News on Google
PJM Interconnection asked the Federal Energy Regulatory Commission on Monday to approve a process it calls Fast Energization, which it says would cut grid connection studies for power plants and large users such as data centres from two years to one. PJM runs the largest US grid. It already serves about 10GW of large computing loads and forecasts up to 30GW more by 2030. Details were first published by PJM Inside Lines.
The proposal, which PJM calls Fast Energization, goes at the main bottleneck for AI infrastructure in the US: getting power to new sites. PJM already serves about 10GW of large computing loads and forecasts up to 30GW more by 2030, and the operator says a shortfall of new generation is already pushing up electricity prices. PJM said it would file at the end of the day on November 16 and asked FERC for a 60-day comment period and an order within 120 days.
Under the plan, PJM would study new generation and new load together instead of in separate processes, which it says removes duplicate work. Readiness and financial requirements would move earlier to screen out speculative projects, and developers would go through quick initial screening rounds so they can decide early whether to commit to the stricter conditions. PJM said it would keep its first-ready, first-served principle.
The filing also creates new transmission services for what PJM calls Large Load customers. These include an interim service that lets a customer connect while network upgrades are still being built, and services for customers that bring their own generation or can reduce their demand. PJM said this follows FERC's finding that some large loads are able to limit their use of the system.
Cost is the other half of the argument. PJM said the proposal gives states transparent access to the cost of transmission upgrades driven by data centres, which would let them bill large loads for those upgrades. It did not set out a specific formula for sharing the costs.
A Second Attempt After October
The filing responds to FERC directives in two dockets on large loads and co-located loads. In October, FERC rejected most of PJM's previous plan for bringing data centres and other large loads onto its system, including a proposed interim service and rules for customers to bring their own new capacity, while approving a large load registry, Utility Dive reported. Part of that plan was denied without prejudice, which left PJM free to file again.
Keeping Data Centres Connected
PJM made a separate filing on Monday aimed at reliability. It would create a category called Large Computational Load for facilities of 50MW or more and require them to ride through voltage and frequency disturbances rather than disconnect. New facilities would have to demonstrate compliance as a condition of connecting and operating. Existing ones would have one year from the effective date, or one year from the start of commercial operation if that is later. PJM proposed an effective date of January 16, 2027.
The trigger was an event on July 22, when nearly 3.9GW of data centres switched from grid power to their own onsite generators after a routine transmission disturbance. PJM said it was the largest such load transfer in its history and that it affected voltages, frequency, power flows and generator behaviour in the Dominion transmission zone and across the Eastern Interconnection. The operator said its control centre handled the event safely, but described the scale and speed of the transfers as serious threats to grid reliability and said ride-through standards would have reduced the impact had they been in place.
PJM said it will keep working with stakeholders on stricter ride-through rules, ramp-rate requirements and other performance standards, drawing on operating experience and any future guidance from FERC or the North American Electric Reliability Corporation. If FERC meets the 120-day timetable PJM requested for the connection plan, a decision would arrive by mid-March 2027.