Energy Transfer has made a final investment decision on its South Mississippi Pipeline, a 215-mile natural gas line expected to cost about $1.6 billion, the company said on November 3 alongside its third-quarter results. Bloomberg reported that the project, which will carry gas from eastern Louisiana across Mississippi, comes as data centres and liquefied natural gas export terminals push up demand for the fuel.
According to the company's earnings release, the pipeline is planned as a 36-inch line able to carry 1.2 billion cubic feet of gas a day, with service projected to start in 2030. Energy Transfer said it has secured long-term, demand-based transportation agreements with shippers. It expects to operate the line and own 51% of it, with the remaining stake held by shippers.
The design may still change. The company said a binding open season to attract more customer commitments is under way, and that the final size and capacity of the pipeline will be set once it closes.
Stronger Quarter and Higher Guidance
Energy Transfer reported adjusted EBITDA of $5.03 billion for the three months to September 30, up from $3.84 billion a year earlier. Net income attributable to partners rose to $1.21 billion from $1.02 billion, and distributable cash flow attributable to partners, as adjusted, increased to $2.52 billion from $1.90 billion. Revenue for the quarter was $37.10 billion, against $19.95 billion a year earlier, according to the income statement.
The partnership raised its full-year 2026 adjusted EBITDA forecast to between $19.7 billion and $19.9 billion, from a previous range of $18.8 billion to $19.1 billion. It expects growth capital spending of $5.4 billion to $5.6 billion this year and about $7 billion in 2027.
The company also reported agreements to supply 150,000 MMBtu a day of firm gas transport from its MRT Pipeline to two power plants under construction in Missouri, starting in late 2027 and mid-2028. The first phase of its Hugh Brinson Pipeline entered full service on September 1, ahead of schedule, with the second phase still planned for the first quarter of 2027.
Energy Transfer declared a quarterly distribution of $0.3425 per common unit, its twentieth consecutive quarterly increase.
Why It Matters
The decision adds to a series of investments by US gas and power companies betting that AI data centres will keep electricity demand rising for years. The earnings release itself does not mention data centres or AI, but the Bloomberg report ties the new line to that demand alongside LNG exports. The same argument is being made in the Gulf: at ADIPEC in Abu Dhabi this week, ADNOC Gas and Eni executives said AI computing will sustain long-term gas demand.
For investors, the 2030 start date is a reminder that the gas and grid infrastructure behind the AI build-out takes years to arrive, even when customers sign long-term contracts.
Sources
- Bloomberg · Energy Transfer Approves $1.6 Billion Gas Pipe as AI Use Soars
- Stock Titan (Energy Transfer press release) · Energy Transfer Reports Third Quarter 2026 Results
- GuruFocus · Energy Transfer LP Q3 2026 Earnings: GAAP EPS of $0.33 Misses Estimates; Revenue Soars to $37.10 Billion
Produced with AI assistance from the sources above. How we work
By
Nakoda News Desk
Nakoda News covers AI and business. Every story links the sources it draws on; how we work is set out in our editorial standards.